Engineering, Procurement and Construction of 400KV Overhead Line Works for GCCIA Oman Direct Link Project
21 Months from the date of Award, from 06th October 2025
ZP.EP194
The Project Scope shall consist of:
Lot 3: Engineering, Procurement and Construction of 400kV Overhead Line Works between
UAE/OMAN Border and GCCIA IBRI Substation, with a total route length of approx. 88 km
- Route survey, data collection, obtaining preliminary NOCs
- Soil investigation including soil resistivity measurement
- Line design / drawings preparation, tower Spotting and optimization
- Design, supply, construction of concrete reinforced pile foundations
- Supply and erection of lattice steel tower structures.
- Supply and installation of new ACSR/AW Finch Conductor 635.5 sqmm as
necessary, complete with all accessories, as necessary.
- Design, supply and installation of new composite shield-wires / OPGW (96 optical
fibers) – 2 Wires,complete with all accessories
- Design, testing, manufacturing, supply and installation of Insulator Sets complete
with RTV Silicone Rubber Coated Glass/Porcelain Insulator Units and all fittings
- Design, supply and installation of Aircraft Warning measures as per the
requirements and regulations of concerned Civil Aviation Authorities in Oman, as
well as with the applicable ICAO Regulations