Construction of 400/132kV Wadi Latham GS and Associated 400kV LILO, and Construction of 132kV Safah GS and Associated OHL “Oxy Network Connection
Twenty-Four (24) months excluding six (6) weeks for mobilization, from 28th July’2025
ZP.EP191
The Project Scope shall consist of:
(A1) Construction of 400/132kV Wadi Latham GS and 400KV LILO.
- 400/132kV Wadi Latham Grid Station shall be constructed under the scope of this
tender within the overall plot identified for 400/132kV GIS Grid Station,
including 11Nos of 400kV GIS Bays,3Nos of 500MVA, 400/132/33kV Power
Transformers, 15Nos of 132kV GIS Bays, 2 Nos of 1000kVA, 33/0.415kV Auxiliary
Transformers,2 Nos of 400KV, 30MVAr Line Shunt Reactors, 2No.of 400KV, 100MVAr
Bus Shunt Reactors, Neutral Reactors, Control & Relay Panels for 400KV & 132KV
Systems,132kV, 1C X 2500Sqmm Cu. XLPE cables & its Termination Accessories
(Outdoor & GIS side), Station Control System (SCS) for 400KV & 132KV System,
Telecom System for 400KV & 132KV System, OLCM & MCMS system, Integrated
Security System, Fire Alarm & Fire Fighting System. EOT cranes for 400KV GIS &
132KV GIS rooms etc
- Existing Sebekhi - Nahada 400kV Double circuit OHL circuits shall be Loop In and
Loop out at Wadi Latham 400kV Grid station including the construction of Gantry,
terminal towers, required angle towers, suspension towers etc. - Route Length: 2 x
36.5Kms
(A2) Construction of 132kV Safah GS and OHL.
- 132kV Safah Grid Station shall be constructed under the scope of this tender within
the overall plot identified for 132kV GIS Grid Station including 8Nos of 132kV GIS
Bays, Control & Relay Panels for 132KV Systems, Two (2) sets of Station Auxiliary
transformers 33/0.415kV, 500kVA with all accessories, 132 kV, underground cable 3
x 1C, 2500 mm2 Cu. XLPE & its Termination accessories suitable for Outdoor &
Indoor, Diesel generator 500 kVA, 0.415 Kv, Station Control System (SCS) for 400KV
& 132KV System, Telecom System for 400KV & 132KV System, OLCM & MCMS
system, Integrated Security System, Fire Alarm & Fire Fighting System, EOT cranes
for 132KV GIS rooms etc
- Construction of 132KV Double circuit OHL between 400/132kV Wadi Latham GS
and Safah 132kV GS. – Route Length: 60 Kms
(A3) Extension of 400kV GIS Bay at Sebekhi 400KV GS and adding Bus Reactor.
- Adding 1No 400kV GIS bay ( Reactor Bay) with LCC, One (1) set of 100 MVAr Busbar
shunt reactor, Reactor Monitoring Systems, Modifications in existing protection,
control, SCS/SCADA etc